Suez Canal Fibre Optic Transmission Crossing with Skywrap

Summary

Egyptian Electricity Transmission Company (EETC) suffered fibre breaks on an existing OPGW network which spanned the Suez Canal. The OPGW cable provided a crucial strategic fibre optic link between the main cities of Egypt and the Sinai peninsular, and an urgent and efficient repair was needed. Tratos SkyWrap® was the best and quickest way of reinstating this important fibre link where the height of the towers and the width of the span over the canal itself made the installation of other cable solutions problematic.

Challenge

This was an extremely complex project requiring careful planning and coordination. A detailed risk analysis was carried out to ensure the safety of the installation crew and to minimise commercial disruption to both the customer and the region. The electricity towers over the canal itself are 220 m tall and only accessible via special lifts. The lines are situated in a military exclusion zone, which makes access very sensitive. The busy canal was in constant use throughout the operation, and no outages were required for the electricity supply.

There were aircraft warning spheres on the line, which had to be removed using a specially adapted trolley to safely support two men who were working 200 m above the canal. A novel fixture system was designed to load the wrapping machines 4 m out on the line ready to start spinning.

Suez Canal Fibre Optic Transmission Crossing with Tratos Skywrap

Solution

Tratos SkyWrap was a unique solution to this difficult installation project as it uses specialist installation equipment to helically wrap fibre optic cable onto the existing OPGW or other earth/phase wires of overhead power lines. Specially designed Tratos SkyWrap fibre optic cable was installed without modification to towers and with little preparation or upfront expense. The installation equipment is light and portable and does not require any special access clearance. Tratos SkyWrap is ideal for installations in difficult terrains, achieving up to 4 km per day.

Results

Using the unique SkyWrap installation system, we were able to provide EETC with a cost effective repair without the complication and major disruption of having to replace the OPGW cable itself.

Related Families

Contact us

Please, don’t hesitate to contact us for additional information on our company or our products.

Related Case Studies

Related Products

Other News

Our website uses cookies and thereby collects information about your visit to improve our website (by analyzing), show you Social Media content and relevant advertisements. Please see our cookies page for further details or agree by clicking the 'Accept' button.

Cookie settings

Below you can choose which kind of cookies you allow on this website. Click on the "Save cookie settings" button to apply your choice.

FunctionalOur website uses functional cookies. These cookies are necessary to let our website work.

AnalyticalOur website uses analytical cookies to make it possible to analyze our website and optimize for the purpose of a.o. the usability.

Social mediaOur website places social media cookies to show you 3rd party content like YouTube and FaceBook. These cookies may track your personal data.

AdvertisingOur website places advertising cookies to show you 3rd party advertisements based on your interests. These cookies may track your personal data.

OtherOur website places 3rd party cookies from other 3rd party services which aren't Analytical, Social media or Advertising.